Heavy! The machinery and load are changed into double layers, and Nanping is connected along the river. Shenzhen plans eight major traffic projects.
Heavy news
this morning
Shenzhen Communications Commission officially released
Optimization of Shenzhen Expressway Network and Layout Planning of Underground Expressway
The first feeling of Tebaojun when he saw the plan was that
work of great writer/calligrapher/painter
Great spirit
Big pattern
Can’t wait to share with you.
Planning scheme of Shenzhen "ten horizontal and thirteen vertical" high-speed road network system
The planning scheme is indeed relatively large.
Summarize a few highlights first-
oneAdd "four horizontal lines" outside the original special zone to form a high-speed road network with "ten horizontal lines and thirteen vertical lines";
2New "one horizontal and three vertical" underground roads in the core area;
threeThe machine-to-load expressway will become a composite channel with two floors;
fourNanping Expressway or underwater interchange with Yanjiang Expressway and west extension docking Shenzhen-Zhuhai Channel;
fiveBinhai Avenue (headquarters base section) was partially sunk and rebuilt.
Shenzhen Municipal Communications Commission introduced,At present, the distance between the east-west high-speed highways outside the former Shenzhen Special Economic Zone is too large, which can no longer meet the current traffic demand.; With the accelerated integration of the special zone, the intensity of development outside the original special zone has increased; In response to the new requirements of regional development in Guangdong-Hong Kong-Macao Greater Bay Area, Shenguanhui and Shenshan Cooperation Zone, the east-west traffic on the second and third floors of Shenzhen will further increase, and the planned east-west high-speed highway can not support the east-west interconnection outside the original special zone.
Learn from the experience of cities and regions such as Hong Kong, Singapore and Tokyo, and follow"Support Guangdong-Hong Kong-Macao Greater Bay Area’s national strategy, promote the integration inside and outside the SAR, improve the structure of high-speed road network and improve the quality of urban life"According to the four principles, Shenzhen will build a high-speed road network system with complete functions, reasonable layout, convenient and efficient, moderate scale and intensive land use, which will serve the whole city, integrate Shenzhen, Huizhou and Greater Bay Area.
Support Guangdong-Hong Kong-Macao Greater Bay Area’s national strategy
In 2017, Guangdong-Hong Kong-Macao Greater Bay Area has become a national strategy, and the connectivity between the East and the West and between cities is the foundation and focus of Greater Bay Area. This expressway optimization fully considers increasing the supply of external channels:
First, the second Shenzhen-Shantou Expressway will be added eastward to connect Shenzhen, Huizhou and Shenzhen-Shantou Cooperation Zone.
Second, in order to match the traffic demand of the deep middle passage under construction, the three-dimensional reconstruction and expansion of the Hefei-Huiyan Expressway.
Third, the second phase of Xiyan Nanping Expressway, after intercommunicating with the expressway along the Yangtze River, reserved the interface of the Shenzhen-Zhuhai-Railway composite channel to the west.
Promote the integration inside and outside the SAR.
In order to balance the layout of the road network outside the original special zone, enhance the traffic service along the expressway, and further promote the integrated development inside and outside the special zone, it is planned to add three east-west passages, namely Baopeng, Baoping and Outer Ring Expressway to extend westward. At the same time of the municipal transformation of Yanba Expressway, the former vertical passage outside the special zone, Longda Expressway and Nanguang Expressway, will be transformed.
Improve the structure of high-speed road network
Drawing on the experience of high-density cities in East Asia such as Tokyo, Hong Kong and Singapore, a certain scale of underground expressway has been added. Along the main axis of urban core development, Dongbin Tunnel will be newly built to connect the cross-sea underground roads along the first line, the Guangzhou-Shenzhen composite channel, the Huanggang composite channel and the eastern transit composite channel.
Improve the quality of urban life
In order to solve the problems that Binhai Avenue can’t meet the traffic pressure caused by the high-intensity development of super headquarters base in the future, the activity space of Shenzhen Bay Park is limited, and the coverage of track, bus and parking facilities is insufficient, and learn from the experience of road subsidence reconstruction in the core areas of advanced cities at home and abroad, such as Madrid M30 Expressway, Shanghai Bund Passage, Guangzhou Zhujiang New Town Linjiang Avenue, etc., a comprehensive reconstruction of Binhai Avenue (headquarters base section) is proposed, which is connected with the road system of headquarters base area in a three-dimensional way.
Detailed explanation of eight high-speed highways planned recently
On June 14th, Shenzhen Municipal Transportation Commission held a press conference, officially released "Shenzhen Expressway Network Optimization and Underground Expressway Layout Planning", and publicly solicited opinions and suggestions from all walks of life and the general public on the planning and design schemes of eight major projects (click for details).Please send feedback to szjtwgh@163.com before July 15th.
I. Reconstruction and Expansion Project of Ji-He and Huiyan Expressway
Drawing lessons from the experience of three-dimensional reconstruction and expansion of Zhongshan Expressway in Taiwan Province, we will build a double-deck composite passage to undertake the functions of transit traffic and urban traffic at different levels, and greatly improve the traffic capacity and efficiency.
1. The upper-level three-dimensional passage mainly adopts bridge viaduct, starting from the deep middle passage in the west and the outer ring expressway in the east, with a total length of 62km, 6 lanes in both directions, 100km/h, and 6 interchanges;
2. The underpass is mainly based on subgrade widening, with partial subgrade changed to bridge, starting from Airport South Road in the west and Lvzi Avenue in the east, with a total length of 60km, 6 lanes in both directions, 80km/h, and 21 interchanges;
3. Through three groups (6 pairs) of up-and-down ramps, the conversion between the upper-level three-dimensional passage and the lower-level ground passage is realized.
Recently, the Guangzhou-Shenzhen Expressway has been implemented to the eastern transit section, with a total length of about 53km.
Second, Nanping quickly connects with the expressway along the Yangtze River and extends westward to connect with the Shenzhen-Zhuhai Channel.
1. The west extension of Nanping Expressway connects with the west bank of the Pearl River, which is conducive to enhancing the regional radiation of Shenzhen central city, especially Qianhai.
2. The rapid connection between Nanping and Yanjiang Expressway can greatly improve the road network structure in western Shenzhen.
3. Preliminary design scheme: The planning focuses on the three schemes of connecting Nanping Expressway and Yanjiang Expressway-elevated interchange at sea, ground interchange in front of sea and land, and underwater interchange. Among them, the underwater interchange scheme has advantages in saving intensive land, improving ecological environment and improving space quality, and can reserve the planning conditions for connecting Shenzhen-Zhuhai channel in the west.
Third, Baopeng Channel
1. Build a new expressway to meet the medium and long distance traffic demand of the group along the route. It starts from the intersection of Binjiang Avenue and Xixiang Avenue in the west and ends at the third phase of Nanping Expressway in the east, with a total length of 53.2km, 6-8 lanes in both directions and a design speed of 60 km/h. The newly-added expressway mainly passes through the built-up area in the form of tunnel (or viaduct), and 16 interchanges are set up with the high-speed expressway intersecting along the line to realize the "fast-fast" connection conversion with the regional high-speed expressway and improve the traffic efficiency.
2. Upgrade and transform the existing main roads, and undertake the functions of traffic connection, traffic distribution and bus main passage in adjacent areas. There are 29 signalized intersections and 59 right-in and right-out intersections. Set up bus lanes (including harbor stops), non-motor vehicle lanes and sidewalks.
Fourth, the municipal reconstruction project of Longda Expressway
The total length of Longda Expressway is 21km, and this reconstruction is divided into three sections. According to the specific conditions of different sections, targeted solutions are put forward.
1. The south section is Shuilang-Fenghuang interchange section, which is about 4.8km long and passes through Shiyan and Guangming South. The main road is widened to two-way eight lanes, and the ground laying method is adopted. Add two-way four-lane auxiliary roads and set up four interchanges;
2. The middle section is the section from Fenghuang to Loucun Interchange, which is about 8.6km long and passes through Gongming and Guangming Center. The main road is widened to two-way eight lanes, and two-way tunnels (or the whole tunnel) are used to lay, adding two-way four-lane auxiliary roads and setting up three interchanges.
3. The northern section is the border section from Loucun to Shenzhen-Dongguan, which is about 7.3km long and passes through Gongming North and Songgang. The main road is widened to two-way eight lanes, and a two-way four-lane auxiliary road is added by ground laying. Set up three interchanges to strengthen the traffic service function of the area along the line; Embankment laying is adopted to ensure the efficiency of main line traffic operation.
V. Municipal Reconstruction Project of Salt Dam
The transformation started in Dameisha and ended in Shenhui border, with a total length of about 31.5 kilometers.
1. The main line is transformed from the existing salt dam expressway, with 6 lanes in both directions and bus lanes, with a design speed of 80 km/h;
2. Set up dual 4-lane auxiliary roads in Dameisha, xiaomeisha, Xiyong, Tuyang and Kwai Chung to disperse vehicles; And set up two full interchanges at Huancheng West Road and Outer Ring Expressway.
Sixth, Qiaocheng East Road North Extension Project
The newly-built Qiaocheng East Road North Extension Passage starts from Longguan Expressway-Fulong Interchange in the north and ends at Binhai Avenue in the south (Shenzhen Bay Tunnel is reserved for the south extension), with a total length of about 17.3km, and the main line has six lanes in both directions. A total of five tunnels are set up, with a total length of 15.5km and the longest tunnel of 6.9km, which is located between Shahe East Road and Beihuan Avenue.
There are 6 interchanges along the line (Fulong Road, Baopeng Passage, Shahe East Road, Nanping Expressway, Beihuan Avenue and Binhai Avenue). Four pairs of tunnel entrances and exits (University Town, Qiaoxiang Road North, Shennan Avenue North) are set up to undertake the medium and long-distance rapid traffic connection between Nanshan, Futian West and Longhua.
Seven, Huanggang Road Rapid Reconstruction Project
1, the new underground tunnel, separation of long and short distance traffic, improve traffic efficiency. The tunnel starts from the original Meiguan toll station in the north and connects to the Guangzhou-Shenzhen Expressway in the south. Four pairs of access ramps are set along the tunnel, with a total length of 11.5km and a design speed of 60km/h, with four lanes in both directions.
2. Transform the ground nodes to improve the overall road capacity. Huanggang Interchange in the North Ring Road was transformed into a full interchange; Huanggang Road-Sungang Road and Huanggang Road-Hongli Road nodes were transformed into rhombic interchanges; Huanggang Road-Zhenhua Road node was transformed into an overpass bridge, and Zhenhua Road overpass bridge was newly built, and the ground was adjusted to a right-in and right-out organization. And widen some ground roads.
Eight, Binhai Avenue (headquarters base section) traffic comprehensive transformation project.
Drawing on the experience of road subsidence reconstruction in the core areas of advanced cities at home and abroad, such as Madrid M30 Expressway, Shanghai Bund Passage, and Guangzhou Zhujiang New Town Linjiang Avenue, Binhai Avenue (headquarters base section) was partially sunken and reconstructed, and it was connected with the road system in the headquarters base area in a three-dimensional way.
Shenzhen will form in the future.
"Ten Horizontal and Thirteen Vertical" High Expressway Network
From south to north, the "Ten Horizons" are Shenzhen Bay Underground Road, Binhai Avenue, Beihuan Avenue, Nanping Expressway, Shenshan Second Expressway, Baopeng Passage, Jihe-Shenshan, Baoping Passage, Outer Ring Expressway and Outer Ring Expressway.
From west to east, the "thirteen verticals" are: Yanjiang Expressway, Binjiang Avenue, Guangzhou-Shenzhen Expressway, Nanguang Road, Fulong-Longda Expressway, Qiaocheng Northeast Extension-Longguan Expressway, Huanggang Road-Meiguan Expressway, Yuping Avenue (Qingping Road), Danping Expressway, East Transit-Huiyan Expressway, Salt Pai Expressway, Yanlong Avenue and Longping Salt Passage.
"ten horizontal and thirteen vertical"
List of high-speed road network system
Note: Bold fonts are newly added for this planning.
Source | Shenzhen Special Zone Daily reporter Pan Weimei